Energy Technology Facility Update
 
                        
                        
                        					
                        
                        Preparation work has begun in the diesel bay of ACEP’s Energy Technology Facility to test Oceana Energy LLC’s hydrokinetic turbine design. In previous years ACEP researchers worked with Oceana on verifying and testing mechanical capabilities of the turbine at the Tanana River Test Site. The current work is focused on grid integration for which the ACEP PSI team has developed grid interface and control specifications and designs which will now be implemented and put to the test in the laboratory.
In order to operate the electric generator in controlled conditions it will not be
                           driven by flowing water but by a motor-gearbox assembly. Currently the mechanical
                           assembly of the turbine testing platform is underway with installation and alignment
                           of the electric generator and motor-gearbox drive in the testing tank taking place.
                           Next researchers will be moving forward with the electrical assembly of the testing
                           platform with testing estimated to take place later this fall to early winter.
Installation and alignment of the electric generator and motor-gearbox drive in the
                              testing tank pictured.  Photo credit D. Light, ACEP/UAF.
 
				